Hope Works Station

Active 0717_HopeW_392
6/16/2017 - 2/1/2018
Created 7/5/2017 by Suzanne Frew
Updated 6/7/2018 by Dave Kresta
48 views • 1 comment

Contact and Funding
Lead Org(s): Snohomish PUD
Primary: Rob Marks
Secondary: Suzanne Frew
Funding: Energy system design funding from BPA and partial construction funding achieved
Overview
Project Objectives:

Net Zero building - Residential portion is expected to meet net zero requirements when complete. Commercial portion may evolve to net zero.

Current Project Phase: Planning
Current Project Status: Ground Breaking for site has took place last month. Unfortunately construction costs continue to increase so commercial portion of building has been reduced as well as some technologies removed from project. Residential units will have radiant wall heaters instead of inverter driven PTHP's, and zonal heat pump water heaters and heat pump dryers appear to still be included.
Outcome
Project Outcome: Not Specified
Notes on Project Outcome: N/A
Additional Information

This is a net zero multi-use building with 2 floors of commercial space and 4 floors of transitional housing. A commercial kitchen will be used for training restaurant and catering skills to those in transition. Additional equipment control features not listed above.

Attached Files
None
Interested / Collaborative RETAC Organizations
N/A
Project Geography
98206
Log in to comment, rate, and share.
Comments (1)
Robert Marks on 06/07/18 on 01:24 PM (Pacific Time)
6-7-18;  Ground Breaking for site has took place last month.  Unfortunately construction costs continue to increase so commercial portion of building has been reduced as well as some technologies removed from project.  Residential units will have radiant wall heaters instead of inverter driven PTHP's, and zonal heat pump water heaters and heat pump dryers appear to still be included. 